The 7 costs most contractors forget to price (and how to catch them)

Estimating · 5 min read

Most jobs don’t lose money on the big, obvious items — the brick, the block, the labour. They lose it on the small things that get missed when you’re pricing late at night. Here are the seven that catch people out most often.

1. Muck-away & disposal

Excavated material has to go somewhere, and tip charges plus haulage add up fast. Remember bulking — dug material swells by roughly 20–30%, so you’re carting away more than the dig volume.

2. Preliminaries

Welfare, skips, scaffolding, temporary power, site set-up, supervision. On a small job these are easy to leave out; on a bigger one they’re a real percentage of the price.

3. Access & working constraints

Tight sites, restricted hours, parking, protecting finished work — all cost time, and time is money you won’t get back once the price is fixed.

4. Waste & wastage

Cutting, breakages and offcuts mean you buy more material than the measured quantity. A few per cent on every line matters by the end.

5. Builder’s work & making good

Chasing, cutting, filling, patching behind other trades — the bits that never make it onto the drawing but always make it onto the job.

6. Testing, commissioning & certification

Air tests, pressure tests, certificates and sign-offs. Small money individually, but a forgotten line is a forgotten cost.

7. Your own margin

The one that hurts most: pricing the work accurately and then forgetting to actually add overheads and profit. Price the job, then protect the margin — separately and deliberately.

How ConstructQS helps: its AI Review reads your estimate and flags likely omissions like these — disposal, prelims, access, thin margin — before you send. It suggests; you decide. See AI Review ›

Day rate vs price-work: quote so you keep the margin

Pricing · 4 min read

“Just give us a day rate” feels simple, but it can quietly cost you. Here’s how to think about it.

When a day rate works

Short, uncertain or investigative work where you can’t pin down the quantity — opening up, making safe, snagging. You’re paid for time, so the risk sits with the client.

When price-work wins

Measurable, repeatable work — brickwork by the m², groundworks by the m³, a run of fencing by the metre. Here, your own productivity is the prize: if your gang beats the rate, the extra is yours.

The trap

Quoting a day rate for work that’s really measurable. If you’re quick, you’ve capped your own earnings; if the job drags, the client argues the hours. Either way you lose the upside.

A simple rule

Measure it if you can. Build the price from quantity × your rate, add prelims, overheads and profit, then present a fixed price. Keep day rates for genuinely unmeasurable work — and write down what a day includes (hours, who, what plant).

How ConstructQS helps: it scopes to your role — a bricklayer prices brickwork, a main contractor prices the whole job — and builds the price from your rates to NET, VAT and GROSS. See the plans ›

How to do a quick take-off from a drawing

Take-off · 4 min read

You don’t need a £10k enterprise package to measure a drawing. The basics are the same whoever you are.

1. Set the scale

Find a known dimension on the sheet — an overall width, a door, a grid. Everything else is measured relative to it. Never scale off a drawing that says “do not scale” without a known figure to calibrate from.

2. Measure in the right units

Lengths in metres, areas in m², volumes in m³, and count the enumerated items (doors, windows, fittings). Group as you go so it maps cleanly to a bill later.

3. Add wastage and check twice

Apply sensible wastage to materials, and sanity-check the big numbers — a floor area that looks wrong usually is.

4. Price from your own rates

Quantities are only half the job. Apply your labour, material and plant rates, then prelims, overheads and profit. A measured quantity at the wrong rate is still the wrong price.

How ConstructQS helps: upload a plan, set the scale by clicking two points on a known dimension, then measure lengths, areas and counts straight off the sheet — and price them from your rates. See Take-off ›